F.C. Library Board Recommends $17 Million Plan That May Not Fit

December 24, 2013 11:21 AM2 comments
IMG_6647

MEMBERS OF THE Mary Riley Styles Library Board of Trustees, led by chairman Bradley E. Gernand, spoke at a work session of the Falls Church Planning Commission last week to outline their proposal for the renovation and expansion of the library. Other members of the board included vice-chair Chester DeLong (far left), Nancy Bentrup, Donald Camp, Jeff Peterson, Sarah Phillips and Edward Rose II. The library director is Mary McMahon (second from right). (Photo: News-Press)

It began to appear as if despite all the shoving, the ugly sister’s foot simply wouldn’t fit into Cinderella’s glass slipper.

The Mary Riley Styles Library Board of Trustees came before the Falls Church Planning Commission at a work session last week to outline its recommendation for a $17 million renovation and expansion of the popular facility on its current site across from Cherry Hill Park and City Hall.

But under a preliminary review by the Planners, it appeared by the conclusion of the session that the combination of objectives the Library Board sought to propose through a renovation at that location simply couldn’t fit on the site.

The board chose its preferred plan based on options after an extensive study and consultation by industry experts – McMillan, Pazdon Smith of Greenville, S.C., Godfrey Associates of Dallas and the ESOARC Studio of Falls Church – that included a modest public survey which showed local residents overwhelmingly favor keeping the library at its present location.

The study seemed to prove more of a negative, than anything else: that the parameters preferred by the Library Board simply won’t work at that location.

Three factors underlay the board’s preference: 1. the current facility is falling apart, it is not in compliance with the Americans With Disabilities Act (ADA), the heating and air conditioning (HVAC) unit and elevators are unreliable, 2. the consultants project an increased use of the facility by 20 to 30 percent in the next 20 years and, 3. citizens appear to strongly favor keeping the library at its current site.

Unlike a scientific or technological research library, which are projected to shrink dramatically in size in coming years due to the Internet, good public libraries will continue to experience considerable increased demand, the consultants said.

That’s because, as in the case of the Mary Riley Styles Library, a quick look at its website or at its bulletin board shows a vast array of programs aimed at early childhood, teen, young adult and adult reading programs and discussion groups. It is the role of a good public library to bring people together, not encourage or allow them to remain isolated in front of a computer screen, and to achieve that, there needs to be a setting that is inclined to draw persons away from their isolation and into a public space to voluntarily share with others.

Therefore, such libraries need to be spacious enough, not only with aisles wide enough and stacks short enough to comply with ADA requirements, but to encourage the gathering and interacting in a learning environment of people of all ages.

The consultants retained by the Library Board seemed to echo these sentiments, and urged that, with a projected increase in use by 20 to 30 percent in the next 20 years, that the present 18,500 square feet usable in the existing building be expanded to 33,000 square feet, or almost double the current space.

Told to limit their work to the present location, they studied expansions in two directions: horizontally, by adding adjacent properties, or vertically, by razing the current building and to building something new that could accommodate a third and fourth floor.

The consultants ruled out a horizontal expansion by finding neighboring property owners simply unwilling to sell, and considering a “eminent domain” option “toxic.”

So, limited to a tear down and rebuild option, that plan still brings the project up short in terms of parking, where it was projected that 37 spaces would be needed.

With underground parking presenting a prohibitive cost, putting parking on the first level would severely limit the benefits of the overall expansion to a third and possibly fourth floor.

The Library Board proposed a new building with three floors (minus parking) and the option to add a fourth floor later. That way, the cost could be limited from $23 million, in the consultants’ projection, to $17 million as an immediate “ask” of the City’s “capital improvement plan” (CIP).

However, “this is a completely unexecutable plan,” said Planning Commissioner Rob Meeks , because the money involved simply does not produce the commensurate gains. “It should be cheaper to relinquish the site and build elsewhere.”

Commissioner Lindy Hockenberry suggested that the current site be retained as a “museum,” or auxiliary to the library, because right how, “It has a lot of history with no where to go.”

She cited a new library in Frederick, Maryland, built in conjunction with a six story parking garage. “Don’t build anything without parking,” she said.

She also criticized the notion of tearing down the existing building and rebuilding it, asking, “It will take two and a half years to rebuild. Where do we move the library in the meantime and how much will that cost?”

As far as just patching up the current site to make it ADA compliant with better elevators and HVAC options, Library Board member Chet DeLong said that would eat up a huge amount of space in the existing library to achieve.

“The City has to come up with other options,” Planning Commissioner Ruth Rodgers concluded.

  • Bradley E. Gernand

    Nick Benton did a great job of summarizing a complex discussion (and I love his opening sentence!).

    If I may add a couple additional important facts to the discussion:

    1. Although many in this country believe public libraries will be disappearing (or downsizing radically) in the future as they revert to online hubs, our study tells us this won’t be what occurs in Falls Church, or in other places like it.

    2. Rather than being able to remain in our existing building with room to spare, we’ll need to add space to it.

    We outgrew our existing building at least five years ago, at the start of the large recession, so we’re only now beginning to call attention to our issue. The issue remains, and in fact grows worse.

    And, finally, in case you’re curious–we didn’t task the study’s authors with examining a possible relation to another property because it’s impossible to analyze a hypothetical. They’ve told us the activity levels and space requirements we’ll see in 20 years’ time, so this valuable information will apply should we ever relocate.

    It has always been in the City’s best interest for us to make our property work as well for us as possible. If the library ever leaves the property it will transfer from public ownership back to the Styles family. We will pursue this option only if requested by City Council–a decision we’re sure would be taken only after a robust, spirited public debate over whether our property should leave City ownership.

    Meanwhile, the study represents our best effort to retain the status quo and make the best use of what we’ve got. I invite the public to visit our website and download the study (it makes for an interesting read!) to see whether you believe we’ve been successful. We believe we have, considering all the constraints upon us.

  • David

    Bradley,

    “Our study” and the subsequent recommendations were produced entirely by consultants who are either library architects or work for companies that partner with such architects. How can we get an objective opinion from a group of individuals who stand to benefit from library renovations?

    Also, if I remember correctly, the survey was exclusively of library users. Of course they are going to want the biggest, best renovations. But what about the taxpayers who don’t use the library often but pay for it? Were their opinions included as well?